Timeline

  • Design for major projects will begin in January 2017. It takes approximately 2 years to design and permit a high school; 15 to 16 months for a middle or elementary school.
     
    Anticipated schedule:
     
    Olympic School (temporary housing for HHS)
    • Begin construction - September 2017
    • Relocate HHS- summer 2018 for the 2018-19 school year 
     
    Highline High School
    • Begin construction - October 2018
    • Open for students - September 2021
     
    New Elementary at Zenith
    • Begin construction - March 2018
    • Open for students - September 2019
     
    New Middle School at Glacier
    • Begin construction - March 2018
    • Open for students -  September 2019