Building the Future at EHS
We are hard at work building your new Evergreen High School. Read about our latest progress and check out the aerial and site photos from October.
We are installing seven large underground concrete vaults to manage stormwater and meet King County permit requirements. You can see one of the vaults visible in the bottom right of photo above.
Construction Progress
- Gym ceiling painted; ductwork installation is underway.
- Science classroom cabinets installed.
- Mass timber beams and columns in the commons sealed.
- Drywall 90% complete; painting ongoing.
- HVAC ductwork and window frames installed on the pedestrian bridge.
- Bathroom ceramic tiling finished.
- Exterior sunshades installed above classroom building windows.
- Hallway wood paneling nearly finished; wood doors being installed.
Next Steps
- Temporary heat will be installed to support drywall and painting.
- Elevator installation beginning in the classroom building.
- Concrete for bus loop curbs and path will be poured in early October.
- Water damage repairs from the May vandalism are ongoing, with the recovery timeline shared on September 20.
We are within budget and on schedule to welcome students in September 2025.
Photos
More
See additional photos in the October 2024 slideshow on the Evergreen project page, and in our October 24 social media posts: