New Answers to Your Bond and Technology Levy Questions 

New Answers to Your Bond and Technology Levy Questions 

We've heard questions from families, staff and community members about the school construction bond and technology levy on the November 3 ballot. We've added answers to our website to help explain the proposed projects and costs. 

Here are some of the questions we've heard. Click each link to explore additional information and more frequently asked questions about that topic.  

Chinook Middle School: Why is Chinook included in the bond if construction won't begin until 2031?  

  • Highline has one interim school site, so the three middle school projects must happen in phases. The $161.3 million project would combine new construction with a full modernization of the remaining buildings. 

Cascade Middle School: Why build at Salmon Creek instead of the current site? 

  • Rebuilding at Salmon Creek is estimated to cost $44 million less. It would also allow students to remain at Cascade during construction. Traffic and neighborhood impacts would be studied during the permitting process. 

CHOICE Academy: What facilities would the new CHOICE Academy include?  

  • Plans include a kitchen and a multipurpose space that could serve as a cafeteria, gym and activity space. School leadership is also exploring options for a library space. 

Critical Needs Funding: What would the $40 million fund?  

  • The proposed funding includes approximately $18.1 million for HVAC, fire and life safety, code and electrical improvements; $5.1 million for roofs; $6.4 million for accessibility improvements at Highline Memorial Stadium; and funding for kitchens, athletic facilities, elevators and security improvements. 

Capital Technology Levy: What would the levy pay for?  

  • The proposed $12 million per year. It would fund cybersecurity, networks, devices, instructional and operational software, technology support and building improvements. The website includes a breakdown of anticipated spending for 2027, the first year of the levy. 

The bond and technology levy are separate propositions. Voters can make an independent decision on each. Each project page has additional FAQs at the bottom. You can also visit our General FAQs for answers to questions about the bond and technology levy. 