Cascade Middle School

Cascade Replacement: $172.1M

Cascade Middle School was built in 1957 and has aging systems and increasing maintenance needs. The campus includes six separate buildings that do not meet today’s safety standards for a single, controlled entry.

The Cascade bond project would replace Cascade Middle School at the Salmon Creek site, located four blocks from the current campus, to provide a more functional and cost‑effective school facility.

A young boy is sitting at a desk, using a laptop and painting with watercolors in a classroom setting with other students visible in the background.

Current Conditions at Cascade Middle School

  • Built in 1957, Cascade has an overall building condition score of 63%, with aging systems and increasing maintenance needs.
  • The campus includes six separate buildings, which do not meet today’s safety standards for a single, controlled entry.
  • Site constraints and setbacks make rebuilding on the current site significantly more expensive.

Why Salmon Creek?

  Salmon Creek Current Site
Cost $172.1M $216.4M
Location 4 blocks away Existing site
Space Flexibility More Limited

Staff, families and students were united in their feedback of rebuilding Cascade at the Salmon Creek site.

Timeline  

With the board's decision to place the Cascade project on the November 2026 ballot, here is a summary of the timeline:  

  • November 2026: Bond measure goes to voters (requires 60% approval).  
  • Early 2027: Design committee convenes and begins an approximately 18- to 22-month design process.  
  • Summer 2028: Design process continues as permitting begins.  
  • Spring 2029: Shark Garden would need to fully vacate the site. 
  • Summer 2029: Construction begins.  
  • Fall 2031: Cascade Middle School opens  