Timelines

2022 Bond

Planning for the three school construction projects began as part of the 2016 bond, which funded the early design work for Evergreen High School, Tyee High School and Pacific Middle School. 

Bond Project Opening
Evergreen High School August 2025
Tyee High School August 2025
Pacific Middle School August 2027
Critical Needs & Improvements Spring 2023 - Summer 2026

2016 Bond

Planning for major projects began in January 2017. Prior to construction, it takes approximately two years to design and permit a high school; 12 to 18 months for an elementary or middle school.

Bond Project Opened
Highline High School August 2021
Glacier Middle School August 2019
Des Moines Elementary August 2019
Olympic Interim School August 2019

Highline High School students attended school at the Olympic Interim School in Des Moines for two years, from fall 2019 to spring 2021. (In response to covid, HHS and all students were in distance learning, starting spring 2020.)

Timeline Information

Prior to construction, it takes approximately two years to design and permit a high school; 12 to 18 months for an elementary or middle school.